Calderbank offer
A Calderbank offer is a settlement offer made on a "without prejudice save as to costs" basis.
It is an approach used to settle a dispute for a lower amount and avoid going to a court trial. It puts one side on notice that if the dispute goes before a court, and the outcome is worse than the Calderbank offer being made, the party making the Calderbank offer is entitled to higher recovery court costs, the fact the offer has been made may also be taken into account when considering the costs awarded.
Important constituents of such an offer are:
- It must be left open for acceptance for 21 days.
- It must offer to pay the other party’s reasonable costs incurred up to the point of acceptance if accepted within 21 days. Thereafter, acceptance being subject to the offeror’s costs incurred after the expiry of the 21 days being paid.
- It must say what is the position as to interest. Normally interest is included.
- It must say whether any counterclaim is taken into account in the offer.
It is named after the case Calderbank v. Calderbank in 1975. Mrs Calderbank before the dispute proceeded to the courts, showed she had a willingness to settle the dispute. If Mr Calderbank had accepted the offer made to him before the trial, he would have been in a better position because the outcome was less favourable to him than Mrs Calderbank’s earlier offer, and then neither would have had to go to court. The court ruled that Mrs Calderbank was entitled to her costs as from the date that she made her willingness to settle known.
It is an alternative to a Part 36 offer, which is a written offer to settle with a period of not less than 21 days during which it can be accepted. If it is not accepted in the stated period and the other party does not beat that offer then there will be costs consequences.
[edit] Related articles on Designing Buildings
- Adjudication.
- Alternative dispute resolution.
- Alternative Dispute Resolution legislation.
- Arbitration Act.
- Arbitration panel.
- Arbitration v Adjudication.
- Arbitration in the construction industry
- Breach of contract.
- Causes of construction disputes.
- Conciliation.
- Construction Industry Model Arbitration Rules CIMAR.
- Contract claims.
- Dispute resolution.
- Dispute resolution boards.
- Dispute resolution procedure.
- Evaluation of claims.
- Expert determination.
- Expert evaluation.
- Housing Grants, Construction and Regeneration Act.
- How does arbitration work?
- How to become an arbitrator.
- Joinder.
- Mediation.
- Part 36 offer
- Pay now argue later.
- Pendulum arbitration.
- Provisional relief.
- The role of the mediator.
- Scheme for Construction Contracts.
- Without prejudice.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Construction Management, 8 July
NEETs crisis drives interest in trades, but apprenticeships barriers remain.
Passive fire protection webinar
MEP services penetration seals.
Where its at podcast (and video) - The role of the Architectural Technologist as an Expert Witness.
More than 200 remarkable buildings added to SAVE’s Buildings at Risk register.
Government scraps pre-application consultation for Nationally Significant Infrastructure Projects.
Historic England and infrastructure
New projects offer opportunities for the historic environment and local communities.
Construction Management, 2 July
Construction deaths halve in two years.
Green Book changes to drive investment in all parts of UK.
Minimum energy efficiency standards (MEES)
CIAT briefing on response to consultations for privately rented non-domestic properties.
Connect, collaborate, shape the future
Registration now live for UK Construction Week Birmingham.
CIOB announces Saul Humphrey FCIOB as new President for 26/27 term.
A quick, simple, and zero-bills solution to prevent overheating.